By Dele Anofi

The federal government has issued a directive to road construction contractors, instructing them to discontinue the use of laterite as a base in road construction.

Instead, the base will now consist of lumps, sharp sand, and stone before laying concrete or asphalt pavement on Federal roads.

- Advertisement -

The Minister of Works, Dave Umahi gave the order at the inauguration of the committee for the supervision of the reconstruction of Benin-Warri dual carriageway and the dualization of East–West Road, Port Harcourt – Onne Port junction road in River State.

The Minister also warned that contract variation would no longer be taken with levity at the Ministry.

In a statement on Friday, October 6, 2023, by Blessing Lere-Adams Director (Information) Press & Public Relations Unit, Federal Ministry of Works (FMW), Umahi noted that laterite has a limited load-bearing capacity, susceptible to erosion and weathering, especially in areas with heavy rainfall and this can lead to degradation of the road surface over time, maintenance challenge and does not last long.

The statement reads in part: “We are giving very serious attention to the roads between Benin and Warri. The road between Eleme and Onne Port, we are mindful of the site conditions of these roads, the water conditions, and the boreholes instead of potholes on these roads. No more laterite, contractors are now to use lumps, sharp sand, and stone base in place of laterite”

“The Minister directed the newly inaugurated Road Taskforce Team that there must be a continuous maintenance of all the roads under construction until the end of the project and should make sure that the contractors are duly informed of the development, and that they should remember that the ministry is under the matching order given by Mr. President to fix Nigerian roads for the citizens to have ease of movement from one location to the other.

- Advertisement -
See also  FG Undertaking 524 Highway, Bridge Projects Nationwide – Fashola

“The committee must implement the contract agreement with maintenance culture as key. Committee members are to monitor the contractors closely to make sure things are done right.

“Our contractors can now understand that we are not insisting that things have to change without a reason, but that the society is demanding the sustainability and integrity of the work they are doing”.

“Umahi disclosed that road infrastructure is one of the key factors for the revolution of our commerce, education, security and power in this country and that Mr. President is committed to our road infrastructure improvement and thus the Ministry is on a mission to uphold the renewed hope agenda of this administration on road infrastructure provision.

“I want to say that road infrastructure is one of the key factors for the revolution of our commerce, education, security and power in this country and Mr. President is committed to our road infrastructure, so we are on a mission and we must take back our country.

- Advertisement -

“The Minister mandated the committee on daily proper supervision and documentation of what the contractors are doing and that they must ensure the new methods of construction are followed including maintenance because it is part of the elements of the project and anything contrary to that attracts punishment.

“We are not at war with the contractor but contractors should not put the public to suffering. Proper daily supervision and documentation of what the contractor is doing is compulsory.

“They must ensure the new method of construction is followed and maintenance follows too because it is part of the elements of the contract and any offence is punishable”

See also  Abiodun: FG Owes Ogun over N300bn on Rehabilitation of Federal Roads

“Umahi ordered that contracts must be stable; no variation (VOP) on the contract will be accepted.

“He charged the contractors using asphalt pavement to ensure that their contracts are stable, sustainable and can stand the test of time and warned that the ministry will not go to the Federal Executive Council (FEC) to ask for increment because of the fluctuating price of bitumen, insisting that the ministry will not go beyond the N6 trillion set aside for the completion of the ongoing projects.”

- Advertisement -

LEAVE A REPLY

Please enter your comment!
Please enter your name here

Related articles

FG engages retired military officers to protect highway construction workers

By Damilola Aina The Federal Government through the Ministry of Works has secured the services of retired military and...

Umahi seeks reconsideration of COREN for Federal Government’s funding

The Minister of Works, Senator David Umahi, on Thursday, disclosed that he had written officially to the appropriate...

We won’t accept shoddy jobs, Umahi warns road contractors

By Dele Anofi President Bola Ahmed Tinubu will not accept substandard road projects, Works Minister David Umahi yesterday warned...